Transport Connectivity Assets Management Project – Provincial Road Development Project – TCAMP-PRDP
Progress Up to 2023.06.31
UVA PROVINCE
UVA PROVINCE
Contract Package | Contractor | Name of Roads | Package Length (km) |
Contract Amount (Without VAT) Rs. Mn. |
Contract Amount (With VAT) Rs. Mn. |
Financial Progress (%) (With Vat) |
Physical Progress (%) | Date of Commencement |
Date of Completion
|
MPCLGS/TCAMP/ PRDP/UV/01 |
VVK-GC Joint Venture |
Kodayana Waththegama Road – 12.6 km |
14.6 | 572.2 | 618 |
99.70% (IPC 30/ Rs.616.70Mn) |
99% | 2020.09.22 |
2023.04.11
|
Hulandawa South Gamunupura Mahamewnawa Road – 2 km |
|||||||||
MPCLGS/TCAMP/ PRDP/UV/03 | JC-NE Joint Venture |
Ambagasdowa Dangamuwa Medawela Road – 4.440 km |
9.47 | 347.1 | 374.9 |
92.48% (IPC18/Rs.346.74Mn) |
100% | 2020.12.11 | 2022.10.25 |
Nugathalawa Jayasuriya Mawatha – 5.030 km |
|||||||||
MPCLGS/TCAMP/ PRDP/UV/05 |
Suhada Enterprises |
Ella Halpe Road 2.17 km |
11.2 | 381.7 | 412.2 |
72.37% |
70% | 2021.09.24 | 2023.05.01 |
Bindunuwewa Badulugasthenna Road – 2.43 km |
(IPC 14/ Rs. 298.32 Mn.) |
||||||||
Dickulpotha Kirioruwa Road – 3.1 km | |||||||||
MarangahawelaKosgama Road – 3.5 km | |||||||||
Total | 35.27 | 1301.0 | 1405.1 |